Final Breakthrough of Head Race Tunnel of SJVN’s Arun-3 Hydro Power Project 900 MW

Shimla, 06 June 2024: Rt. Hon’ble Prime Minister of Nepal Shri Pushpa Kamal Dahal ‘Prachanda’ triggered the last blast to mark the completion of heading excavation 11.8 km long Head Race Tunnel of 900 MW Arun-3 Hydro Electric Project in Sankhuwasabha District of Nepal.

Arun-3 HEP will start generation by next year and will generate 3924 MU of electricity every year. We are grateful for the unwavering support from the Government of Nepal, local authorities, and the community,” said Shri Sushil Sharma.

Shri Sushil Sharma, CMD SJVN briefed to the Hon’ble PM of Nepal about the progress of under construction 900 MW Arun 3 HEP & 217 km long associated Transmission Line. Further Shri Sushil Sharma, CMD informed that more than 74% of the project works have already been completed.